Project Description:
SPRINGFIELD- ROADWAY RECONSTRUCTION ON PARKER STREET INCLUDING BRIDGE REPLACEMENT, BR# S-24-020 CONRAIL OVER PARKER STREET
The proposed project is the reconstruction of approximately 5,540 feet of Parker Street, from Boston Road to Main Street, including 250 feet of Verge Street, and 400 feet of Oak Street, resulting in a total roadway reconstruction of approximately 6,190 linear feet. The new CSX bridge carrying three tracks over Parker Street will be raised to provide more roof clearance for vehicular traffic under the bridge. The new longer bridge will also eliminate the current 30 foot wide underpass roadway bottleneck on Parker Street. The new underpass section will be increased to widened to 64 feet, which consists of two turning lanes, two through traffic lanes, and two sidewalks. This major north/south inner city transportation and commercial artery carries an ADT approaching 31,000. The project also entails geometric improvements and the upgrade of existing signalization, and new signalization with pedestrian activation at intersection crossings along Parker Street.
Location:
  • City of Springfield
  • Resident Engineer: Michael McCabe
    Construction Contract Value: $11,019,397.70
    Construction Bid Price: $10,633,520.00
    Initial Construction Estimate: $8,153,543.79
    District: District 2

    Contracts (1) Progress
    # 38132 -- Construction Contract
    Springfield - Roadway reconstruction on Parker street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/15/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/29/1993
    Project Review Committee PRC Approved 02/08/1994
    Project Status Advertised 09/20/2003
    Project Management
    100% Design 100% Package Received 05/22/2002
    100% Design 100% Package Comments to DE 08/20/2002
    Final Design PS&E Received 08/05/2003
    Final Design PS&E to FAPRO 09/08/2003