Project Description:
WORCESTER- SIGNAL & INTERSECTION IMPROVEMENTS AT CAMBRIDGE STREET AND SOUTHBRIDGE STREET
This project will enhance safety and improve efficiency by installing improved traffic signals at the intersection of Cambridge Street and Southbridge Street and by installing new traffic signals at the intersection of Southbridge Street and Riverside Street. These two traffic signals will be coordinated to allow for a more efficient flow of traffic. Roadway widening on Southbridge Street will allow for five lanes of travel at the Cambridge Street intersection. Also at that intersection, there will be geometric improvements to the turning radii, particularly at the corner where St. Matthew's Parish is located. There will be some minor widening of Riverside Street to provide for a two-lane (left turn and right turn) approach to Southbridge Street and there will be a lane reconfiguration (with no actual widening) of McKeon Road to provide for a two-lane (left turn and right turn) approach to Cambridge Street. Also at the intersection of Southbridge Street and College Street, the timing of the traffic signals will be improved to ease traffic congestion.
Location:
  • City of Worcester
  • Resident Engineer: Jeffrey Gorczynski
    Construction Contract Value: $2,139,006.00
    Construction Bid Price: $1,816,260.00
    Initial Construction Estimate: $1,780,534.50
    District: District 3

    Contracts (2) Progress
    # 56606 -- Construction Contract
    Worcester - Roadway Reconstruction and Related Work at Southbridge (Route 12) and Cambridge Streets Completed
    # 99081 -- Design -- Traffic Open End
    Statewide - Assist Traffic Engineering with Traffic Control Device Improvement Projects Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/24/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/31/1994
    Project Review Committee PRC Approved 02/08/1994
    Project Status Advertised 06/28/2008
    Project Management
    100% Design 100% Package Received 05/14/2007
    100% Design 100% Package Comments to DE 08/29/2007
    25% Design 25% Package Received 12/23/2004
    25% Design 25% Package Comments to DE 02/18/2005
    25% Design Design Public Hearing 04/28/2005
    Final Design PS&E Received 02/05/2008
    Final Design PS&E Received 05/13/2008
    Final Design PS&E to FAPRO 05/14/2008
    Consultant Contract Process Scope to DE 09/23/2004
    Consultant Contract Process NTP Issued 09/29/2004