Project Description: |
RAYNHAM- TAUNTON- RECONSTRUCTION AND WIDENING OF ROUTE 44 (7300 FT.) INCLUDING BR# R-02-010 AND R-02-011
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | Other |
Project Manager: | Manhar Patel![]() |
Estimated Total Contract Cost: | $3,980,423.88 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|