Project Description:
TOPSFIELD- SIGNAL UPGRADE, NEWBURYPORT TURNPIKE (ROUTE 1) AT HIGH STREET (ROUTE 97)
The recommended improvements for this project consist of replacing the existing traffic signal equipment with a fully actuated traffic control signal system. Along with replacing the traffic control signal equipment, existing signs and pavement markings will be upgraded.
Location:
  • Town of Topsfield
  • Resident Engineer: Philip Jodoin
    Construction Contract Value: $831,393.11
    Construction Bid Price: $640,103.11
    Initial Construction Estimate: $527,968.59
    District: District 4
    Current Status: This project is now complete. (as of 11/21/2008)

    Contracts (2) Progress
    # 50285 -- Construction Contract
    Topsfield - Intersection Improvements Including Signals at Route 1 (Newburyport Turnpike) and Route 97 (High Street) Completed
    # 99081 -- Design -- Traffic Open End
    Statewide - Assist Traffic Engineering with Traffic Control Device Improvement Projects Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/08/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is now complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/28/1994
    Project Review Committee PRC Approved 02/08/1994
    Project Review Committee Letter 05/06/1994
    Project Status Advertised 07/01/2006
    Project Management
    100% Design 100% Package Received 12/23/2004
    100% Design 100% Package Comments to DE 09/23/2005
    25% Design 25% Package Received 01/28/1997
    25% Design 25% Package Comments to DE 06/13/1997
    25% Design Design Public Hearing 08/20/1997
    75% Design 75% Package Received 11/06/1998
    75% Design 75% Package Comments to DE 02/08/1999
    Final Design PS&E Received 01/05/2006
    Final Design PS&E to FAPRO 05/05/2006