Project Description: |
STURBRIDGE- HIGHWAY LIGHTING IMPROVEMENTS ROUTE I-84/ROUTE 20
This project will replace 18 high mast lighting poles, luminaires, lowering devices and wire. Also, 20 underpass luminaires and related conduit runs will be replaced. Power connections will be installed for a flashing beacon, two traffic control flashers at the East & West Access Road and two flood lights located at the State Police barracks.
|
Location: |
|
Resident Engineer: | Paul Thompson |
Construction Contract Value: | $1,322,852.00 |
Construction Bid Price: | $1,138,229.75 |
Initial Construction Estimate: | $912,297.75 |
District: | District 3 |
Current Status: | All underground conduit and wiring is complete. Contractor is waiting for delivery of light poles. (as of 11/10/2004) |
|