CHARLEMONT- BRIDGE REHABILITATION, C-05-005, ROUTE 8A (NORTH HEATH ROAD) OVER MILL BROOK (BISSELL BRIDGE)
The scope of work for the design contract consists of rehabilitating the existing bridge while maintaining its historic characteristics, adding crash tested bridge rail and upgrading live loads to meeting applicable load requirements.
Location:
  • Town of Charlemont
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $3,068,508.00
    Construction Bid Price: $2,785,280.00
    Initial Construction Estimate: $2,760,726.00
    District: District 1

    Contracts (3) Progress
    # 33313 -- Design -- Bridge Rehab/Recon/New Const
    Rehabilitation and Analysis/Design of the Bissell Bridge located on Rte.8A. Final
    # 51216 -- Construction Contract
    Charlemont Completed
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/22/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 06/24/2006
    Project Management
    100% Design 100% Package Received 08/10/2005
    100% Design 100% Package Comments to DE 11/30/2005
    25% Design 25% Package Received 04/06/2005
    25% Design 25% Package Comments to DE 04/18/2005
    25% Design Design Public Hearing 04/28/2005
    75% Design 75% Package Received 06/08/2005
    75% Design 75% Package Comments to DE 07/12/2005
    Final Design PS&E Received 12/06/2005
    Final Design PS&E to FAPRO 12/12/2005
    Consultant Contract Process Scope to DE 09/18/2003
    Consultant Contract Process NTP Issued 10/31/2003