Project Description:
ACUSHNET- BRIDGE REPLACEMENTS, A-03-003 (3M5), A-03-007 (AJH) & A-03-008 (AJJ), HAMLIN STREET OVER THE ACUSHNET RIVER
The work includes the replacement of the existing bridges which carry Hamlin Street over the Acushnet River. The replacement of this town-owned bridge consists of replacing one bridge and two culverts. The project also includes roadway reconstruction in the vicinity of the bridge. The project will be coordinated with the local fish ladder project organization, “Hands Across the River”.
Location:
  • Town of Acushnet
  • Construction Begins: Summer 2022
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $4,788,735.80
    District: District 5
    Current Status: • Loam and seed were completed on 4/8/25. • V-notch in headwall at auxiliary culvert was installed on 4/23/25. • Placement of asphalt top course was done on 4/24/25. • Saw and seal were completed on 4/28/25. • Line striping and road opening were done on 4/30/25. • Final Walk-Through was completed on 5/1/25. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 05/23/2025)

    Contracts (2) Progress
    # 118622 -- Construction Contract
    Replacement of Bridge No. A-03-003 and Culvert No. A-03-008 and Removal of Br. No. A-03-007 Hamlin Street over the Acushnet River 100% Complete
    # 77883 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/02/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    • Loam and seed were completed on 4/8/25. • V-notch in headwall at auxiliary culvert was installed on 4/23/25. • Placement of asphalt top course was done on 4/24/25. • Saw and seal were completed on 4/28/25. • Line striping and road opening were done on 4/30/25. • Final Walk-Through was completed on 5/1/25. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/12/1997
    Project Review Committee PRC Approved 01/13/1998
    Project Review Committee Letter 07/13/1998
    Project Status Advertised 06/18/2022
    Project Management
    100% Design 100% Package Received 09/24/2020
    25% Design 25% Package Received 01/25/2018
    25% Design 25% Package Received - Resub 1 05/07/2019
    25% Design Design Public Hearing 09/27/2018
    75% Design 75% Package Received 06/01/2020
    75% Design 75% Package Comments to DE 07/07/2020
    Final Design PS&E Received 11/25/2020
    Final Design Peer Review Comments to DE 04/06/2022
    Final Design PS&E Received - Resub 1 03/07/2022
    Final Design PS&E Received - Resub 4 04/18/2022