Project Description:
TEMPLETON- RECONSTRUCTION OF ROUTE 101 (DUDLEY/PETERSHAM ROAD) 2.1 MILES
The project consists of reconstructing Dudley Road (Route 101) from the Phillipston town line to the junction of Route 2A. Proposed improvements on this town-owned roadway include new roadway pavement, sidewalks, curbing, drainage and some widening.
Location:
  • Town of Templeton
  • Resident Engineer: Jane Trudeau
    Construction Contract Value: $5,044,530.67
    Construction Bid Price: $4,372,086.00
    Initial Construction Estimate: $3,584,145.00
    District: District 2
    Current Status: Roadway under construction (as of 09/12/2006)
    Additional Info: Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 03/24/2008)

    Contracts (1) Progress
    # 42840 -- Construction Contract
    Templeton - Route 101 (Dudley Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/24/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Roadway under construction
    Additional Info
    Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/07/1994
    Project Review Committee PRC Approved 05/24/1994
    Project Status Advertised 05/14/2005
    Project Management
    100% Design 100% Package Received 06/19/1998
    100% Design 100% Plans Complete 07/28/1998
    25% Design 25% Package Received 11/01/1996
    25% Design 25% Package Comments to DE 03/27/1997
    25% Design Design Public Hearing 02/20/1997
    75% Design 75% Package Received 07/24/1997
    75% Design 75% Package Comments to DE 10/15/1997
    Final Design PS&E Received 12/01/2004
    Final Design PS&E to FAPRO 05/05/2005