| Project Description: |
TEMPLETON- RECONSTRUCTION OF ROUTE 101 (DUDLEY/PETERSHAM ROAD) 2.1 MILES
The project consists of reconstructing Dudley Road (Route 101) from the Phillipston town line to the junction of Route 2A. Proposed improvements on this town-owned roadway include new roadway pavement, sidewalks, curbing, drainage and some widening.
|
| Location: |
|
| Resident Engineer: | Jane Trudeau![]() |
| Construction Contract Value: | $5,044,530.67 |
| Construction Bid Price: | $4,372,086.00 |
| Initial Construction Estimate: | $3,584,145.00 |
| District: | District 2 |
| Current Status: | Roadway under construction (as of 09/12/2006) |
| Additional Info: | Daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 03/24/2008) |
|