Project Description:
SHELBURNE- ROADWAY RECONSTRUCTION AND RELATED WORK ON A SECTION OF COLRAIN/SHELBURNE ROAD
Location:
  • Town of Shelburne
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Project Manager: Martin Leelman
    Estimated Total Contract Cost: $1,193,816.80
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project