Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ASHFIELD- RESURFACING AND RELATED WORK ON A SECTION OF WILLIAMSBURG ROAD
Location:
  • Town of Ashfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: Brian Haggerty
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 06/23/2001 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/18/1994
    Project Review Committee PRC Approved 08/15/1994
    Project Status Advertised 06/23/2001
    Project Management