Project Description:
CHESTER- BRIDGE REPLACEMENT, C-11-023, SMITH ROAD OVER THE MAIN BRANCH OF THE WESTFIELD RIVER
The proposed project consists of replacing the existing historic bridge. The new bridge will be prestressed concrete box beams supported on new abutments on a new alignment, 35-feet north of the existing bridge. The proposed bridge will be approximately 85-feet long, 20-feet wide. The existing bridge will remain open during construction.
Location:
  • Town of Chester
  • Resident Engineer: Richard Miskinis Jr
    Construction Contract Value: $921,508.00
    Construction Bid Price: $796,825.70
    Initial Construction Estimate: $638,538.00
    District: District 1

    Contracts (1) Progress
    # 54020 -- Construction Contract
    Chester - Bridge Replacement -(C-11-051) Smith Road over the Middle Branch of the Westfield River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/28/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 05/17/2006
    100% Design 100% Package Comments to DE 07/24/2006
    25% Design 25% Package Received 04/26/2005
    25% Design 25% Package Comments to DE 05/26/2005
    25% Design Design Public Hearing 07/11/2005
    75% Design 75% Package Received 12/30/2005
    75% Design 75% Package Comments to DE 03/03/2006
    Final Design PS&E Received 01/30/2007
    Final Design PS&E to FAPRO 08/16/2007
    Consultant Contract Process Scope to DE 09/17/2003
    Consultant Contract Process NTP Issued 10/30/2003
    Consultant Contract Process Workhours Approved 10/10/2003