Project Description:
HAVERHILL- BRIDGE REPLACEMENT, BR# H-12-006, UPPER BRIDGE STREET OVER THE MERRIMACK RIVER (JOSEPH C. COMEAU BRIDGE)
This project proposes the replacement of the existing bridge which will be closed during construction, utilizing a short detour. A total of approximately 300 feet of approach roadway work is included. A temporary pedestrian/utility bridge will be erected for the duration of this construction project.
Location:
  • City of Haverhill
  • Resident Engineer: David Conroy
    Construction Contract Value: $20,281,760.00
    Construction Bid Price: $17,884,692.00
    Initial Construction Estimate: $18,334,882.00
    District: District 4
    Current Status: Contractor has completed all items including punch list items. MHD personnel has prepared and submitted finals package. (as of 01/17/2008)

    Contracts (1) Progress
    # 33276 -- Construction Contract
    Bridge Replacement H-12-6 (Steel) - Upper County Bridge over the Merrimac River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/30/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor has completed all items including punch list items. MHD personnel has prepared and submitted finals package.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 10/26/2002
    Project Management
    100% Design 100% Package Received 06/29/2001
    100% Design 100% Plans Approved 08/13/2002
    25% Design 25% Package Received 05/02/1996
    25% Design Design Public Hearing 03/04/1998
    75% Design 75% Package Received 01/06/2001
    75% Design 75% Package Comments to DE 05/28/2001
    75% Design 75% Plans Complete 06/01/2001
    Final Design PS&E Received 09/10/2002
    Final Design PS&E to FAPRO 09/10/2002
    Consultant Contract Process Scope to DE 08/12/1994
    Consultant Contract Process NTP Issued 06/23/1995