Project Description: |
LEOMINSTER- BRIDGE REPLACEMENT, L-08-003, MECHANIC STREET OVER THE NORTH NASHUA RIVER
The purpose of this project is to replace the existing structurally deficient bridge along with its sidewalks and bridge approaches.
|
Location: |
|
Resident Engineer: | Ryan Davison |
Construction Contract Value: | $4,356,177.35 |
Construction Bid Price: | $3,783,807.00 |
Initial Construction Estimate: | $4,242,976.00 |
District: | District 3 |
|