Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORWOOD- SUPERSTRUCTURE REPLACEMENTS, BR# N-25-022 NAHATAN ST. (SOUTH) OVER ROUTE 1 & N-25-023 NAHANTAN ST. (NORTH) OVER ROUTE 1
This project will result in the demolition and replacement of both of the Nahatan Street bridges over Route 1 NB and SB at the same location. The length of the project is approximately 715 feet. Included in this project is the reconstruction of the roadway approaches, new granite curbing and guardrail.
Location:
  • Town of Norwood
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $3,721,721.74
    Construction Bid Price: $3,433,787.00
    Initial Construction Estimate: $4,066,000.00
    District: District 5

    Contracts (1) Progress
    # 33201 -- Construction Contract
    2 Bridge Replacements N-25-22, N-25-23 (Steel) - Nahatan Street (North & South) over U. S. Route 1. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/30/2003
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/15/2001
    Project Status Advertised 10/05/2002