| Project Description: |
FALL RIVER- SOMERSET- BRIDGE REPLACEMENT, BR# F-02-001=S-16-004 BRIGHTMAN STREET OVER TAUNTON RIVER (CONTRACT 3)
This is the third construction contract out of the four total construction contracts for this bridge replacement project. This portion proposes to construct the foundation on which the new bridge will be placed. Adjacent roadway embankment work is also included.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Other |
| Project Manager: | Martin Leelman![]() |
| Estimated Total Contract Cost: | $36,180,940.03 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|