Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FALL RIVER- SOMERSET- BRIDGE REPLACEMENT, BR# F-02-001=S-16-004 BRIGHTMAN STREET OVER TAUNTON RIVER (CONTRACT 3)
This is the third construction contract out of the four total construction contracts for this bridge replacement project. This portion proposes to construct the foundation on which the new bridge will be placed. Adjacent roadway embankment work is also included.
Location:
  • City of Fall River
  • Town of Somerset
  • Resident Engineer: Lloyd Simpson
    Construction Contract Value: $36,180,940.03
    Construction Bid Price: $32,637,671.50
    Initial Construction Estimate: $36,095,000.00
    District: District 5

    Contracts (2) Progress
    # 31065 -- Design -- Hwy Eng Open End
    Fall River/ Somerset - Construction Services Final
    # 31157 -- Construction Contract
    Bridge Replacement (Substructures and Related Work) - Brightman Street (Contract 3). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/08/2001
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/16/2000
    Project Management