Project Description:
CAMBRIDGE- SOMERVILLE- BELMONT- BIKEWAY CONSTRUCTION AT ALEWIFE STATION, INCLUDES PEDESTRIAN BRIDGE
The proposed project consists of construction of a bicycle path from Somerville to Belmont. This project will physically and visually connect the proposed work with the existing sections of path improving the continuity of the bike path. The project starts at the end of the Somerville Bicycle Path, continues through Davis Square, and follows Linear Park to Alewife Station in Cambridge where it will connect with Minuteman Path. At Alewife, a new bridge will be constructed over the Alewife Brook and the path will continue to Brighton Road in Belmont.
Location:
  • Town of Belmont
  • City of Cambridge
  • City of Somerville
  • Resident Engineer: Peter Jodoin
    Construction Contract Value: $3,954,676.25
    Construction Bid Price: $3,330,508.32
    Initial Construction Estimate: $4,666,696.00
    District: District 4

    Contracts (5) Progress
    # 54828 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open basis for various statewide highway and bridge projects. Final
    # 57729 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60148 -- Construction Contract
    Bike Path Constrution and Related Work Including Pedestrian Bridge (C-01-027). Completed
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 97408 -- Design -- Bike/Ped Projects
    Somerville/Cambridge/Belmont-Bike Path Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/01/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/08/2006
    Project Status Advertised 07/18/2009
    Project Management
    100% Design 100% Package Received 01/22/2009
    100% Design 100% Package Comments to DE 04/28/2009
    25% Design 25% Package Received 05/25/1999
    25% Design Design Public Hearing 05/13/2004
    25% Design 25% Plans Complete 04/21/2004
    75% Design 75% Package Received 04/10/2007
    75% Design 75% Package Comments to DE 09/27/2007
    Final Design PS&E Received 06/15/2009
    Final Design PS&E to FAPRO 07/15/2009
    Consultant Contract Process Scope to DE 01/01/1997
    Consultant Contract Process NTP Issued 01/01/1998