Project Description:
WESTFIELD- BRIDGE REHABILITATIONS, BR# W-25-003, ROUTE 20 OVER POWDER MILL BROOK AND W-25-004 ROUTE 20 OVER THE WESTFIELD RIVER
The purpose of this project is to replace the Route 20 bridges over the Powder Mill Brook and the Westfield River. The new Westfield River bridge will be a three-span steel girder bridge, 113 meters in length. The Powder Mill Book bridge will be a five-span steel girder bridge, 134 meters in length. The existing bridges will be demolished.
Location:
  • City of Westfield
  • Resident Engineer: Edward King
    Construction Contract Value: $14,598,178.49
    Construction Bid Price: $13,195,961.00
    Initial Construction Estimate: $13,900,000.00
    District: District 2
    Current Status: Physical work completed (as of 11/04/2005)

    Contracts (1) Progress
    # 33120 -- Construction Contract
    2 Bridge Replacements W-25-3 (Steel) W-25-4 (Steel) - Route 20 over the Powder Mill Brook and the Westfield River. RE-ADVERTISED as a FEDERAL AID PROJECT. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/24/2002
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/16/1999
    Project Review Committee PRC Approved 05/24/1994
    Project Status Advertised 03/30/2002
    Project Status Advertised 08/10/2002
    Project Management