Project Description:
BOSTON- BRIDGE REHABILITATION, B-16-237, MASSACHUSETTS AVENUE (ROUTE 2A) OVER COMMONWEALTH AVENUE
This project will rehabilitate the Massachusetts Avenue Bridge that spans Commonwealth Avenue with a new bridge superstructure on existing substructure..
Location:
  • City of Boston
  • Construction Begins: Autumn 2016
    Resident Engineer: Kevin Laramee
    Construction Bid Price: $7,372,607.00
    District: District 6

    Contracts (1) Progress
    # 96914 -- Construction Contract
    Bridge Superstructure Replacement Br. No. B-16-237 (Pre-Fabricated Bridge Units) Massachusetts Avenue (Route 2A) over Commonwealth Avenue Bypass (Route 2). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/07/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 05/24/1994
    Project Review Committee PRC Approved 08/15/1994
    Project Review Committee Letter 08/29/1994
    Project Status Advertised 08/13/2016
    Project Management
    100% Design 100% Package Received 08/10/2015
    100% Design 100% Package Comments to DE 09/10/2015
    25% Design 25% Package Received 06/10/2014
    25% Design 25% Package Comments to DE 07/03/2014
    25% Design 25% Package Comments to DE 10/15/2014
    25% Design Design Public Hearing 03/25/2015
    75% Design 75% Package Received 03/16/2015
    75% Design 75% Package Comments to DE 05/18/2015
    Final Design PS&E Received 04/15/2016
    Final Design PS&E to FAPRO 08/05/2016