Project Description: |
NEW BEDFORD- RECONSTRUCTION OF ROUTE 18 (ACUSHNET AVENUE) FROM MM 4.7 TO MM 6.5 (9600 FT)
The proposed project consists of reconstructing Acushnet Avenue, in the City of New Bedford, from the Route 140 Connector northerly to Braley Road (approximately 9,500 feet). The work will include new pavement, new sidewalks and granite curbing, and drainage improvements
|
Location: |
|
Resident Engineer: | Alfredo Nunez |
Construction Contract Value: | $5,023,590.55 |
Construction Bid Price: | $3,873,000.00 |
Initial Construction Estimate: | $5,424,891.00 |
District: | District 5 |
|