Project Description:
WORCESTER- ROUTE 146 PROJECT, ROUTE I-290, QUINSIGAMOND AVENUE COMPLEX (BROSNIHAN SQUARE)
The project entails the construction of the I-290/ Route 146 (Brosnihan Square) interchange. The work includes the construction of 1 mile of Route 146, 1.3 miles of I-290 and 1.1 miles of local roads. The work also includes five bridges, retaining walls, traffic signals, lighting and extensive landscaping.
Location:
  • City of Worcester
  • Resident Engineer: Jeffrey Gorczynski
    Construction Contract Value: $60,975,119.00
    Construction Bid Price: $54,095,926.95
    Initial Construction Estimate: $57,139,111.00
    District: District 3
    Current Status: Work is complete on the series of 4 bridges on I-290 Eastbound, Milbury Street, and Route 146. Once demolition is completed on the Westbound side, new bridge construction is anticipated to begin on the Westbound side. (as of 01/08/2007)

    Contracts (4) Progress
    # 36494 -- Construction Contract
    Worcester - Interchange Construction - Interstate 290 (Brosnihan Square) Completed
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/14/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work is complete on the series of 4 bridges on I-290 Eastbound, Milbury Street, and Route 146. Once demolition is completed on the Westbound side, new bridge construction is anticipated to begin on the Westbound side.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/15/1994
    Project Status Advertised 05/29/2004
    Project Status Advertised 08/07/2004
    Project Management
    100% Design 100% Package Received 10/03/2003
    100% Design 100% Package Comments to DE 12/29/2003
    75% Design 75% Package Received 02/28/2002
    75% Design 75% Package Comments to DE 08/06/2002
    Final Design PS&E Received 05/26/2004
    Final Design PS&E to FAPRO 05/26/2004