Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- RT.146 PROJECT, RT.146 SEGMENT FROM WALL 12 NORTH TO RT.I-290/QUINSIGAMOND AVENUE (HURLEY SQUARE) INCL. 5 BRIDGES
The project entails construction of 1 mile segment of Route 146 between Providence Street and Brosnihan Square and reconstruction of 2 miles of local streets. The work also includes four bridges, retaining walls, traffic signals, lighting and landscaping.
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $47,113,785.52
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • W44058 
    • W44153 
    • W44154 
    • W44159 
    • W44161 
    See the Milestone Details tab for additional Project information