WESTFIELD- BRIDGE REHABILITATION, W-25-010, W-25-022 & CONSTRUCTION OF NEW BRIDGE, W-25-052 (GREAT RIVER BRIDGE)
The project involves the reconstruction/rehabilitation of the existing Great River Bridge, which carries Route 10/202 over the Westfield River. The project also includes the construction of a new bridge crossing 150 feet down-stream of the existing bridge, the reconstruction of the Pochassic Street Bridge and the reconstruction of the existing CSX owned viaduct structure. Under the preferred alternative there will be a coordinated traffic signal system interconnected with adjacent signals along the Elm Street corridor. Additionally there will be geometric improvements to the project area intersections and adjacent streets to better accommodate peak hour traffic demands.
Location:
  • City of Westfield
  • Resident Engineer: Michael Los
    Construction Contract Value: $62,849,861.00
    Construction Bid Price: $54,740,943.85
    Initial Construction Estimate: $50,050,428.00
    District: District 2

    Contracts (2) Progress
    # 49909 -- Construction Contract
    Westfield - Great River Bridge Project. Route 10/202. Completed
    # 64320 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/27/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/17/1994
    Project Status Advertised 09/24/2005
    Project Status Advertised 09/23/2006
    Project Status Advertised 11/11/2006
    Project Management
    100% Design 100% Package Received 07/06/2004
    100% Design 100% Package Comments to DE 05/25/2005
    Final Design PS&E Received 09/06/2005
    Final Design PS&E to FAPRO 09/06/2005