Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLYOKE- BRIDGE REPLACEMENTS, H-21-014, ROUTE 141 (APPLETON STREET) OVER SECOND LEVEL CANAL & H-21-020 OVER FIRST LEVEL CANAL
This project involves replacing two bridges on Route 141 (Appleton Street) where the bridges cross over the First Level and Second Level Canals. The new bridges will be two-span concrete bridges supported by abutments that will be constructed behind the existing canal walls. The existing roadway and sidewalk widths will be maintained. A decorative bridge rail will be installed that is compatible with the proposed Holyoke Canalwalk and the historic character of the area. This requires that a roadway curb rail be used to separate the roadway from the sidewalk and pedestrian rails as the proposed bridge rail is not a crash tested acceptable design.
Location:
  • City of Holyoke
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Alwin Ramirez
    Estimated Total Contract Cost: $20,935,603.75
    Estimated Total Federal Participating Construction Cost: $22,289,561.80
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Received (as of 06/24/2024 )

    Contracts (2) Progress
    # 36805 -- Design -- Footprint Bridge contracts
    (Footprint 5 Preservation) Perform design of deficient State and /or muncipally owned bridges as part of the Bridge Rehabilitation/Reconstruction Preservation Program. Final
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLYOKE
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $8,034,819.20
    State Cost: $2,008,704.80
    Total Cost: $10,043,524.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/16/1999
    Project Review Committee PRC Tabled 08/15/1994
    Project Review Committee PRC Approved 10/17/1994
    Project Review Committee Letter 10/21/1994
    Project Management
    25% Design 25% Package Received 06/24/2024
    25% Design 25% Package Comments to DE 08/23/2004
    25% Design Design Public Hearing 06/14/2007
    75% Design 75% Package Comments to DE 11/15/2009
    Consultant Contract Process Scope to DE 09/08/1999
    Consultant Contract Process NTP Issued 01/16/2001