Project Description:
HOLYOKE- BRIDGE REPLACEMENT, H-21-018, LYMAN STREET OVER FIRST LEVEL CANAL
The purpose of this project is to replace the Lyman Street Bridge over the First Canal. Sidewalks will be included on each side of the proposed bridge.
Location:
  • City of Holyoke
  • Construction Begins: Spring 2019
    Resident Engineer: John Dahl
    Construction Bid Price: $6,594,524.50
    District: District 2

    Contracts (5) Progress
    # 105926 -- Construction Contract
    Bridge Replacement Br. No. H-21-018 (Steel) Lyman Street over the First Level Canal Completed
    # 32174 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract G Final
    # 69765 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77891 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/17/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/21/1999
    Project Review Committee PRC Tabled 08/15/1994
    Project Review Committee PRC Approved 10/17/1994
    Project Review Committee Letter 10/21/1994
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 06/08/2018
    100% Design 100% Package Comments to DE 07/10/2018
    100% Design 100% Plans Approved 08/08/2018
    100% Design 100% Plans Complete 08/23/2018
    25% Design 25% Package Received 02/28/2008
    25% Design 25% Package Received 04/11/2017
    25% Design 25% Package Comments to DE 06/02/2017
    25% Design Design Public Hearing 09/21/2017
    75% Design 75% Package Received 02/22/2018
    75% Design 75% Package Comments to DE 03/26/2018
    Final Design PS&E Received 08/24/2018
    Final Design PS&E to FAPRO 08/29/2018
    Consultant Contract Process Scope to DE 01/22/2004
    Consultant Contract Process NTP Issued 03/04/2005