BOSTON- BRIDGE REHABILITATION, B-16-217, AMERICAN LEGION HIGHWAY OVER ROUTE 203 (MORTON STREET)
The proposed bridge rehabilitation includes repair of the existing bridge abutments along with replacement of deteriorated steel truss members. Minor approach work will include guardrail, pavement markings and minor repair to the historical bridge rail and elliptical trusses. The bridge will continue to be closed during the construction period and a detour will be in place.
|
Location: |
|
Resident Engineer: | Ahmad Ilyas |
Construction Contract Value: | $7,923,809.00 |
Construction Bid Price: | $5,041,098.40 |
Initial Construction Estimate: | $2,158,000.00 |
District: | District 6 |
|