BOSTON- BRIDGE REHABILITATION, B-16-217, AMERICAN LEGION HIGHWAY OVER ROUTE 203 (MORTON STREET)
The proposed bridge rehabilitation includes repair of the existing bridge abutments along with replacement of deteriorated steel truss members. Minor approach work will include guardrail, pavement markings and minor repair to the historical bridge rail and elliptical trusses. The bridge will continue to be closed during the construction period and a detour will be in place.
Location:
  • City of Boston
  • Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $7,923,809.00
    Construction Bid Price: $5,041,098.40
    Initial Construction Estimate: $2,158,000.00
    District: District 6

    Contracts (1) Progress
    # 58085 -- Construction Contract
    BOSTON-Bridge Superstructure Replalcement Br. No. B-16-217 (Steel) American Legion Highway over Route 203 (Morton Street) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/14/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/15/1994
    Project Status Advertised 06/23/2001
    Project Status Advertised 12/29/2001
    Project Status Advertised 12/20/2008
    Project Management
    100% Design 100% Package Received 10/21/2008
    100% Design 100% Package Comments to DE 11/14/2008
    25% Design 25% Package Received 07/28/2006
    25% Design 25% Package Comments to DE 10/23/2007
    25% Design Design Public Hearing 12/05/2006
    75% Design 75% Package Received 02/29/2008
    75% Design 75% Package Comments to DE 09/29/2008
    Final Design PS&E Received 11/26/2008
    Final Design PS&E to FAPRO 12/17/2008