Project Description: |
FRANKLIN- 3R PROJECT UNION STREET FROM BEAVER ST TO WASHINGTON STREET (1.0 MILE)
The reconstruction of Union Street also includes two concrete sidewalks with granite curbs, wheelchair ramps, geometric and drainage improvements, pavement markings and signs to improve vehicular and pedestrian safety.
|
Location: |
|
Resident Engineer: | Julio Fontecchio |
Construction Contract Value: | $4,118,879.00 |
Construction Bid Price: | $3,747,435.00 |
Initial Construction Estimate: | $3,501,825.00 |
District: | District 3 |
Current Status: | Working on punch list items (as of 10/22/2007) |
|