Project Description:
FRANKLIN- 3R PROJECT UNION STREET FROM BEAVER ST TO WASHINGTON STREET (1.0 MILE)
The reconstruction of Union Street also includes two concrete sidewalks with granite curbs, wheelchair ramps, geometric and drainage improvements, pavement markings and signs to improve vehicular and pedestrian safety.
Location:
  • Town of Franklin
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $4,118,879.00
    Construction Bid Price: $3,747,435.00
    Initial Construction Estimate: $3,501,825.00
    District: District 3
    Current Status: Working on punch list items (as of 10/22/2007)

    Contracts (1) Progress
    # 39722 -- Construction Contract
    Franklin - Union Street Roadway Reconstruction Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/09/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Working on punch list items
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/17/1994
    Project Status Advertised 01/01/2005
    Project Management
    100% Design 100% Package Received 05/29/2003
    100% Design 100% Package Comments to DE 03/30/2004
    25% Design 25% Package Received 11/22/1996
    25% Design 25% Package Comments to DE 12/20/1996
    25% Design Design Public Hearing 05/06/1997
    75% Design 75% Package Received 08/18/1997
    75% Design 75% Package Comments to DE 12/01/1997
    Final Design PS&E Received 10/25/2004
    Final Design PS&E to FAPRO 12/28/2004