Project Description:
GROVELAND- HAVERHILL- BRIDGE REPLACEMENT, G-15-001=H-12-012, ROUTE 97 & ROUTE 113 OVER THE MERRIMACK RIVER (BATES BRIDGE)
This project consists primarily of the replacement of the existing Bates Bridge with a new bridge located approximately 60 feet downstream from the existing bridge. This will allow the existing bridge to remain in service during construction. The proposed bridge will have a movable span similar to the existing bridge. In addition to the 775 feet long bridge, the project also includes reconstruction of the approach roadways in the City of Haverhill and the Town of Groveland to tie the new bridge alignment in with the existing approach roadways. The approach work extends approximately 500 feet beyond the bridge in Haverhill, and 300 feet in Groveland.
Location:
  • Town of Groveland
  • City of Haverhill
  • Resident Engineer: Vincent DeAngelo
    Construction Contract Value: $49,756,810.00
    Construction Bid Price: $45,151,100.25
    Initial Construction Estimate: $65,169,242.00
    District: District 4

    Contracts (8) Progress
    # 54827 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57729 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60204 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of completing Construction Phase Services during the construction of the Groveland/Haverhill Bates Bridge. Final
    # 61344 -- Construction Contract
    Bridge Replacement (Bates Bridge) (G-15-001=H-12-012) (Steel) - Routes 97 &113 over the Merrimack River. Completed
    # 62938 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering for various projects .
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/27/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/17/1994
    Project Status Advertised 08/01/2009
    Project Management
    100% Design 100% Package Received 02/28/2007
    100% Design 100% Package Comments to DE 07/16/2007
    25% Design 25% Package Received 03/07/2002
    25% Design 25% Package Comments to DE 05/06/2002
    25% Design Design Public Hearing 05/22/2002
    75% Design 75% Package Received 01/10/2003
    75% Design 75% Package Comments to DE 02/09/2004
    Final Design PS&E Received 02/23/2009
    Final Design PS&E to FAPRO 07/08/2009
    Consultant Contract Process Scope to DE 08/04/1997
    Consultant Contract Process NTP Issued 10/25/1999