Project Description:
WESTFORD- INTERSECTION IMPROVEMENTS AT ROUTE 110 (LITTLETON ROAD) AND POWERS ROAD
The proposed project entails the reconstruction of four intersections in the Town of Westford: Littleton Road (Route 110) and Concord Road (Route 225) west (Location 1); Littleton Road (Route 110) and Concord Road (Route 225) east (Location 2); Littleton Road (Route 110) and Power Road (Location 3); and Concord Road (Route 225) and Power Road, (Location 4). Locations 1, 3 & 4 will be signalized. Components of this project may now be constructed as mitigation by a private developer for Westford Technology Park. Therefore the project will be modified based on the extent of Westford Technology Park's required mitigation.
Location:
  • Town of Westford
  • Resident Engineer: Patrick Marion
    Construction Contract Value: $1,103,100.47
    Construction Bid Price: $956,609.30
    Initial Construction Estimate: $1,095,000.00
    District: District 3

    Contracts (1) Progress
    # 57291 -- Construction Contract
    Westford - Intersection Improvements Route 110 (Littleton Road) at Powers Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/22/2009
    Contract Information
    Project Designer: Other
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/15/1998
    Project Review Committee PRC Tabled 10/31/2001
    Project Review Committee PRC Tabled 12/14/2006
    Project Review Committee PRC Approved 02/07/1995
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee PRC Denied 11/04/2002
    Project Review Committee Letter 03/21/2007
    Project Status Advertised 09/06/2008
    Project Management
    25% Design 25% Package Received 06/13/2007
    25% Design 25% Package Comments to DE 11/30/2007
    25% Design Design Public Hearing 04/15/2008
    75% Design 75% Package Received 05/05/2008
    Final Design PS&E Received 08/21/2008
    Final Design PS&E to FAPRO 09/03/2008