Project Description:
WINCHESTER- SIGNAL & IMPROVEMENTS AT 4 LOCATIONS ON CHURCH STREET & ROUTE 3 (CAMBRIDGE STREET)
This project will enhance safety and improve efficiency by installing new traffic signals at the intersection of Cambridge St. (Route 3) and Pond St. and the intersection of Cambridge St., Everett Ave. and Myopia Rd. Also, the existing traffic signals at the intersection of Cambridge St. and Church St./High St. and the intersection of Church St. and Bacon St./Fletcher St. will be replaced and new turning lanes will be added for greater efficiency of flow. The intersection of Cambridge St. and Church St./High St. and the intersection of Cambridge St. and Everett Ave and Myopia Rd. will be coordinated to further improve traffic flow.
Location:
  • Town of Winchester
  • Resident Engineer: Martin McGowan
    Construction Contract Value: $2,664,346.00
    Construction Bid Price: $2,372,370.00
    Initial Construction Estimate: $2,014,000.00
    District: District 4

    Contracts (5) Progress
    # 48664 -- Design -- Traffic Signing/Signals
    Work will generally consist of preparing Plans, Specs and Estimate for intersection improv. and traffic signal installations associated with the Hwy Safety Improv. Prg (HSIP). Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85023 -- Construction Contract
    Intersection Improvements and Signal Replacements at 4 Locations along Cambridge (Route 3) and Church Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/06/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 07/03/2013
    100% Design 100% Package Comments to DE 11/01/2013
    25% Design 25% Package Received 01/29/2002
    25% Design 25% Package Comments to DE 03/14/2002
    25% Design Design Public Hearing 04/24/2002
    75% Design 75% Package Received 11/18/2003
    75% Design 75% Package Comments to DE 03/14/2005
    Final Design PS&E Received 07/31/2014
    Final Design PS&E Received 09/12/2014
    Final Design PS&E to Peer Reviewer 08/27/2014
    Final Design Peer Review Comments to DE 09/15/2014
    Final Design PS&E to FAPRO 09/17/2014
    Consultant Contract Process Scope to DE 01/17/2008
    Consultant Contract Process NTP Issued 06/18/2008
    Consultant Contract Process Workhours Approved 06/03/2008