Project Description:
FALL RIVER- WESTPORT- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-195 AND RAMPS
This project includes repaving, safety improvements and bridge rehabilitation on the Interstate System. Work also includes geometric improvements to the Route 24SB / I-195EB ramps to extend the acceleration lane on the on-ramp which enters onto the high speed (left ) lane of I-195 EB .
Location:
  • City of Fall River
  • Town of Westport
  • Resident Engineer: Gregory Nicholas
    Construction Contract Value: $4,711,167.00
    Construction Bid Price: $5,792,065.50
    Initial Construction Estimate: $4,582,820.00
    District: District 5

    Contracts (1) Progress
    # 42274 -- Construction Contract
    Work consists of cold planning, resurfacing and related work on Route I-195 and ramps in the City of Fall River and the Town of Westport. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/24/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 04/23/2005
    Project Management
    100% Design 100% Package Received 02/23/2005
    Final Design PS&E Received 03/31/2005
    Final Design PS&E to FAPRO 03/31/2005