| Project Description: |
FALL RIVER- WESTPORT- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-195 AND RAMPS
This project includes repaving, safety improvements and bridge rehabilitation on the Interstate System. Work also includes geometric improvements to the Route 24SB / I-195EB ramps to extend the acceleration lane on the on-ramp which enters onto the high speed (left ) lane of I-195 EB .
|
| Location: |
|
| Resident Engineer: | Gregory Nicholas![]() |
| Construction Contract Value: | $4,711,167.00 |
| Construction Bid Price: | $5,792,065.50 |
| Initial Construction Estimate: | $4,582,820.00 |
| District: | District 5 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||