MILLIS- ROADWAY RECONSTRUCTION AND RELATED WORK ON A SECTION OF ROUTE 109 (MAIN STREET)
This project will result in the reconstruction of Route 109 from Spring Street to the Medfield Town Line for approximately 2.4 miles. The reconstruction of this roadway includes bituminous concrete roadway pavement, cement concrete and brick sidewalks, and granite curbing, construction of extensive drainage system improvements, traffic signals, ornamental lighting, traffic signs, pavement markings, guardrail, tree plantings, and other miscellaneous improvements.
Location:
  • Town of Millis
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $5,385,197.57
    Construction Bid Price: $4,664,608.00
    Initial Construction Estimate: $4,670,000.00
    District: District 3

    Contracts (1) Progress
    # 33194 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Main Street (Route 109). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/22/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/09/1994
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 08/17/2002
    Project Management