PITTSFIELD- RESURFACING & TRAFFIC SIGNAL IMPROVEMENTS ON ROUTE 7 (SOUTH STREET) FROM BERKSHIRE LIFE TO TACONIC STREET
The project as proposed would resurface or replace full depth pavement on South Street from south of South Mountain Road to just north of Reed Street, a distance of 1.1 miles. Included in the project would be pavement repair, cold planing and overlay, full depth replacement, sidewalk repair, traffic signal improvements and pavement markings.
Location:
  • City of Pittsfield
  • Resident Engineer: Russell Duval
    Construction Contract Value: $5,716,647.00
    Construction Bid Price: $5,011,744.20
    Initial Construction Estimate: $5,128,279.20
    District: District 1

    Contracts (3) Progress
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71094 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Route 7 (South Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/05/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 05/27/2011
    25% Design 25% Package Received 08/10/2009
    25% Design 25% Package Received 05/17/2010
    25% Design 25% Package Received 07/30/2010
    25% Design 25% Package Comments to DE 12/02/2009
    25% Design 25% Package Rejected 06/24/2010
    25% Design Design Public Hearing 01/27/2011
    75% Design 75% Package Received 05/27/2011
    Final Design PS&E Received 08/15/2011
    Final Design PS&E to FAPRO 09/13/2011
    Consultant Contract Process Scope to DE 01/10/2008