DEDHAM- BRIDGE REHABILITATION, D-05-004, ROUTE 109 (BRIDGE STREET) OVER THE CHARLES RIVER
This project will replace the Route 109 over the Charles River bridge superstructure and its supporting abutments. It will include the construction of new concrete abutments supported by steel piles and new piers supported by concrete piles. The approach roadway from approximately 725 feet towards west and 500 feet towards east will also be reconstructed. Westbound traffic will be maintained by a temporary bridge and Eastbound traffic will use half the bridge during construction. Pedestrians will be required to use the temporary bridge during construction.
Location:
  • Town of Dedham
  • Resident Engineer: Eric Zilinsky
    Construction Contract Value: $5,665,875.00
    Construction Bid Price: $4,926,123.00
    Initial Construction Estimate: $4,558,120.50
    District: District 4

    Contracts (3) Progress
    # 30270 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 57634 -- Construction Contract
    Bridge Rehabilitation (D-05-004) (Concrete) - Route 109 (Bridge Street) over the Charles River. Completed
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/18/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 07/19/2008
    Project Status Advertised 09/13/2008
    Project Management
    100% Design 100% Package Received 06/05/2006
    100% Design 100% Package Received 05/08/2007
    100% Design 100% Package Comments to DE 07/26/2006
    100% Design 100% Package Comments to DE 08/06/2007
    25% Design 25% Package Received 05/08/2000
    25% Design 25% Package Comments to DE 03/13/2001
    75% Design 75% Package Received 12/28/2001
    75% Design 75% Package Comments to DE 07/28/2003
    Final Design PS&E Received 12/19/2007
    Final Design PS&E to FAPRO 12/26/2007
    Consultant Contract Process NTP Issued 10/21/1997