Project Description:
TEWKSBURY- SIGNAL RECONSTRUCTION, ROUTE 38 (MAIN STREET) AT SHAWSHEEN STREET
The purpose of the proposed project is to improve and upgrade the existing intersection geometry, increase intersection capacity and to provide safer and more efficient operation for both the pedestrians and motor vehicles. This project is located at the intersection of Route 38 with Shawsheen Street in Tewksbury. The Route 38 limits extend from the vicinity of Livingston Street on the west to the bridge over the Shawsheen River to the east. The Shawsheen Street project limits are approximately 140 meters (460 feet) south of the intersection to 165 meters (540 feet) north of the intersection.
Location:
  • Town of Tewksbury
  • Resident Engineer: William Murphy
    Construction Contract Value: $1,904,364.00
    Construction Bid Price: $1,484,422.00
    Initial Construction Estimate: $1,262,744.50
    District: District 4
    Current Status: This project is complete. (as of 01/31/2008)

    Contracts (2) Progress
    # 30203 -- Design -- Traffic Signing/Signals
    Statewide - Traffic engineering services with traffic signal improvement projects. Final
    # 36886 -- Construction Contract
    Traffic Signal Upgrade - Main St (Rte. 38) at Shawsheen St. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/18/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/31/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 07/31/2004
    Project Management
    Final Design PS&E Received 05/17/2004
    Final Design PS&E to FAPRO 05/17/2004