Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MARLBOROUGH- ROADWAY RECONSTRUCTION INCLUDING SIGNALS, ROUTE 20 (BOSTON POST ROAD) FROM THE NORTHBORO CL TO FELTON ST.
This project consists of improvements to Route 20 in Marlborough from the Northborough town line to the southbound ramps of Interstate 495, a distance of 1.4 miles. The project also includes improvements and upgrades to the nearby Route 20 and Williams Street intersection. The project will alleviate existing roadway and intersection capacity and safety deficiencies, as well as accommodate anticipated traffic growth along this segment of Route 20.
Location:
  • City of Marlborough
  • Design Responsibility: Other
    Right of Way Responsibility: Other
    Project Manager: Kimberley Sloan
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 09/29/2001 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/25/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 09/29/2001
    Project Management