Project Description:
SOUTHAMPTON- RESURFACING AND RELATED WORK ON POMEROY MEADOW ROAD FROM ROUTE 10 TO THE EASTHAMPTON TL
Location:
  • Town of Southampton
  • Resident Engineer: Jane Trudeau
    Construction Contract Value: $2,290,803.00
    Construction Bid Price: $1,998,730.00
    Initial Construction Estimate: $2,027,000.00
    District: District 2
    Current Status: Physical work completed. (as of 11/04/2004)

    Contracts (1) Progress
    # 33028 -- Construction Contract
    Resurfacing and Related Work on a Section of Pomeroy Meadow Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/04/2002
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/30/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 04/27/2002
    Project Management