Project Description:
WARWICK- BRIDGE REPLACEMENT, W-08-004, ROUTE 78 (ORANGE ROAD) OVER ORCUTT BROOK
The work for this project consists of replacing the Route 78 (Orange Road) Bridge over the Orcutt Brook with a single span concrete arch bridge along with new bridge rail. The substructure is anticipated to be a new reinforced concrete abutment placed on rock. The profile of the bridge will remain essentially the same. The curb to curb width of the bridge will be 26 feet. A single lane temporary bridge and temporary signal will be constructed directly adjacent to the existing bridge to maintain traffic during construction.
Location:
  • Town of Warwick
  • Resident Engineer: Jeffrey Hendricks
    Construction Contract Value: $1,285,600.00
    Construction Bid Price: $1,232,000.00
    Initial Construction Estimate: $1,534,521.00
    District: District 2
    Current Status: Bridge under construction. (as of 05/19/2008)

    Contracts (2) Progress
    # 32165 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract A Final
    # 51612 -- Construction Contract
    Warwick - Bridge Replacement Route 78 (Orange Road) over Orcutt Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/24/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/26/1995
    Project Review Committee PRC Approved 02/07/1995
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 03/31/2006
    100% Design 100% Package Comments to DE 06/14/2006
    25% Design 25% Package Received 07/07/2004
    25% Design 25% Package Comments to DE 10/13/2004
    25% Design Design Public Hearing 11/30/2004
    75% Design 75% Package Received 03/21/2005
    75% Design 75% Package Comments to DE 09/08/2005
    Final Design PS&E Received 08/15/2006
    Final Design PS&E to FAPRO 08/31/2006
    Consultant Contract Process NTP Issued 11/25/2003