BERNARDSTON- BRIDGE REHABILITATION, BR# B-10-012, ROUTES 5 & 10 (SOUTH STREET) OVER B&M RR
The new 3-span bridge will provide more clearance for the tops of the trains passing underneath. Both new piers will be built further back than the existing piers to provide more clearance for the sides of trains. The new bridge will have two 12-foot travel lanes, two 11-foot shoulders, and two 6.5-foot sidewalks.
Location:
  • Town of Bernardston
  • Resident Engineer: Sean Sullivan
    Construction Contract Value: $4,745,066.00
    Construction Bid Price: $4,597,062.00
    Initial Construction Estimate: $3,470,308.45
    District: District 2
    Current Status: Bridge under construction (as of 05/11/2007)
    Additional Info: Permanent lane restrictions/reductions for the duration of the project. Alternating one-way traffic controlled by temporary traffic signal. (as of 03/05/2007)

    Contracts (1) Progress
    # 49437 -- Construction Contract
    Bernardston - Bridge Replacement - (B-10-012) (Steel) - Rte 5 (South Street) and Rte 10 over B&M Railroad Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/11/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction
    Additional Info
    Permanent lane restrictions/reductions for the duration of the project. Alternating one-way traffic controlled by temporary traffic signal.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/20/1999
    Project Review Committee PRC Approved 04/11/1995
    Project Status Advertised 06/04/2005
    Project Management
    100% Design 100% Package Received 03/18/2005
    100% Design 100% Package Comments to DE 05/10/2005
    25% Design 25% Package Received 09/04/2002
    25% Design 25% Package Comments to DE 11/19/2002
    25% Design Design Public Hearing 05/12/2004
    75% Design 75% Package Received 09/21/2004
    75% Design 75% Package Comments to DE 01/06/2005
    Final Design PS&E Received 05/27/2005
    Final Design PS&E to FAPRO 05/27/2005
    Consultant Contract Process NTP Issued 05/10/2002