Project Description:
GREENFIELD- MONTAGUE- BRIDGE REHABILITATION, G-12-020=M-28-001, MONTAGUE CITY ROAD OVER CONNECTICUT RIVER (GENERAL PIERCE BRIDGE)
The purpose of this project is to rehabilitate the existing structurally deficient bridge and improve the condition of the bridge approaches.
Location:
  • Town of Greenfield
  • Town of Montague
  • Construction Begins: Summer 2020
    Resident Engineer: Joseph Burek
    Construction Bid Price: $13,787,742.50
    District: District 2

    Contracts (3) Progress
    # 111028 -- Construction Contract
    Bridge Rehabilitation (Including Painting) Br. No. G-12-020=M-28-001 (General Pierce Bridge) Montague City Road over the Connecticut River Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/11/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/11/1995
    Project Review Committee PRC Approved 04/11/1995
    Project Status Advertised 03/14/2020
    Project Management
    100% Design 100% Package Received 02/03/2020
    100% Design 100% Package Comments to DE 02/21/2020
    75% Design 75% Package Received 11/27/2019
    75% Design 75% Package Comments to DE 12/27/2019
    Final Design PS&E Received 03/02/2020
    Final Design PS&E to FAPRO 03/09/2020