Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ERVING- MONTAGUE- BRIDGE REHABILITATION, BR# E-10-001=M-28-014 EAST MINERAL ROAD OVER THE MILLERS RIVER (CONVERSION TO PED/BIKE)
The existing bridge, constructed in 1888, is composed of two spans. The approach span, reconstructed in 1939, is 52 feet long and has steel stringers with a reinforced concrete deck. The 105 foot main span is a pin connected Pratt truss with wrought iron floor beams. It will be rehabilitated and repainted to maintain a 12.5 foot wide crossing for pedestrian, bicycle and horses.
Location:
  • Town of Erving
  • Town of Montague
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $812,780.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • E10001 
    • M28014 
    See the Milestone Details tab for additional Project information