Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- ROADWAY RECONSTRUCTION AND RELATED WORK ON CAMBRIDGE, WASHINGTON AND TREMONT STREETS
Location:
  • City of Boston
  • Resident Engineer: Ken Lim
    Construction Contract Value: $10,818,937.69
    Initial Construction Estimate: $9,372,757.70
    District: District 4

    Contracts (1) Progress
    # 99096 -- Construction Contract
    CAMBRIDGE ST, WASHINGTON ST, TREMONT ST Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/09/1998
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/11/1995
    Project Status Advertised 07/18/1998
    Project Management