Project Description:
DARTMOUTH- NEW BEDFORD- IMPROVEMENTS ON DARTMOUTH STREET, FROM ROCKDALE AVENUE TO ROGER STREET (3R PROJECT)
The revised project limits now include the section of Dartmouth Street between Rockdale Avenue and Cove Road thereby creating a continuous project from the Rockdale Avenue to the Rogers Street Intersection. Approximately 1400 LF. of roadway will be added to the project. The improvements at the three intersections are: 1) Dartmouth Street at Rockdale Avenue - install a new fully actuated traffic signal for the left-turn phase with pavement widening on the Rockdale Avenue eastbound & westbound right-turn lanes. Left turns will be prohibited when exiting from the Bank of America/McDonalds driveway onto Rockdale Avenue. 2) Dartmouth Street at Cove Road/GarfieldStreet/Russells Mills Road. Work at this location will include the installation of traffic signals coordinated with location number 3. Russell Mills Road will be converted to a two-way roadway and a new dedicated right-turn lane will be constructed for the Dartmouth Street southbound approach at the Cove Road intersection. 3) Dartmouth Street at Rodgers Street. All three new traffic signals will include a protected pedestrian phase, and all three intersections will include new cross walks, wheelchair ramps and sidewalk improvements on all approaches.
Location:
  • Town of Dartmouth
  • City of New Bedford
  • Resident Engineer: Francis Grenon
    Construction Contract Value: $1,728,635.87
    Construction Bid Price: $1,460,000.00
    Initial Construction Estimate: $2,140,855.00
    District: District 5

    Contracts (1) Progress
    # 60209 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Dartmouth Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/08/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/06/1995
    Project Status Advertised 08/22/2009
    Project Management
    100% Design 100% Package Received 01/20/2009
    100% Design 100% Package Comments to DE 03/27/2009
    25% Design 25% Package Received 09/16/2005
    25% Design 25% Package Comments to DE 05/11/2006
    25% Design Design Public Hearing 02/12/1998
    75% Design 75% Package Received 03/26/2008
    75% Design 75% Package Comments to DE 09/30/2008
    Final Design PS&E Received 08/10/2009
    Final Design PS&E to FAPRO 08/19/2009