Project Description:
WESTWOOD- RECONSTRUCTION, ROUTE 109 (HIGH STREET) FROM GROVE STREET TO HARTFORD STREET (8,780 FEET)
This project proposes to reconstruct High Street utilizing full depth reconstruction. Included are sidewalks, walls, drainage, curbing, signs and pavement markings. New traffic signals will be installed at Hartford Street, Gay Street, Windsor Road/Public Library Entrance and Summer Street. The project will accommodate bicycles and be fully handicapped accessible. Extensive landscaping and site furnishings are also included.
Location:
  • Town of Westwood
  • Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $4,440,082.36
    Construction Bid Price: $4,479,548.00
    Initial Construction Estimate: $4,349,928.25
    District: District 4
    Current Status: This project is currently complete with only punchlist work remaining on the traffic signals. (as of 08/08/2007)

    Contracts (1) Progress
    # 37043 -- Construction Contract
    Westwood - Route 109 (High Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/07/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is currently complete with only punchlist work remaining on the traffic signals.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/11/1995
    Project Status Approved 25% 12/01/1999
    Project Status Advertised 08/14/2004
    Project Management
    100% Design 100% Package Received 04/10/2003
    100% Design 100% Package Comments to DE 09/24/2003
    25% Design 25% Package Received 12/23/1998
    25% Design 25% Package Comments to DE 06/14/1999
    25% Design Design Public Hearing 12/01/1999
    75% Design 75% Package Received 01/29/2000
    75% Design 75% Package Comments to DE 07/30/2001
    75% Design 75% Plans Complete 03/15/2002
    Final Design PS&E Received 07/09/2004
    Final Design PS&E to FAPRO 07/09/2004