LEE- RECONSTRUCTION OF TYRINGHAM ROAD, FROM THE TYRINGHAM T.L. TO ROUTE 102 (2.0 MILES)
The purpose of this project is to rehabilitate and improve Tyringham Road through minor widening and the installation of a closed drainage system. The work includes the construction of retaining walls, a new sidewalk and new guardrails. Traffic control signs will be replaced as necessary.
Location:
  • Town of Lee
  • Resident Engineer: Darin Aitken
    Construction Contract Value: $5,069,492.00
    Construction Bid Price: $4,365,003.50
    Initial Construction Estimate: $4,866,697.00
    District: District 1

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79503 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Tyringham Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/24/1995
    Project Review Committee PRC Approved 05/02/1995
    Project Review Committee Letter 05/24/1995
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 06/06/2011
    100% Design 100% Package Comments to DE 12/22/2011
    25% Design 25% Package Received 11/14/2003
    25% Design 25% Package Received 06/09/2008
    25% Design 25% Package Received 12/09/2008
    25% Design 25% Package Rejected 07/17/2008
    25% Design 25% Package Approved 07/28/2009
    25% Design Design Public Hearing 09/22/2009
    75% Design 75% Package Received 12/21/2009
    75% Design 75% Package Comments to DE 02/19/2010
    Final Design PS&E Received 05/18/2012
    Final Design PS&E Received 03/22/2013
    Final Design PS&E Received 06/24/2013
    Final Design PS&E Received 08/20/2013
    Final Design PS&E to FAPRO 08/27/2013