Project Description:
SOUTHWICK- BRIDGE REPLACEMENT, S-22-005, ROUTE 202/ROUTE 10 OVER JOHNSON BROOK
The proposed project consists of the replacement of the bridge which carries U.S. Route 202 and State Route 10 over the Johnson Brook in the same alignment. This replacement will be constructed in three stages. The work will also include improvements to the approach roadway and the relocation of the existing water main.
Location:
  • Town of Southwick
  • Resident Engineer: Sean Sullivan
    Construction Contract Value: $2,492,838.00
    Construction Bid Price: $2,047,686.00
    Initial Construction Estimate: $2,727,594.00
    District: District 2

    Contracts (4) Progress
    # 57723 -- Design -- Bridge Open End
    Work will consist of final design and construction phase services including a Bridge Rating for US Route 202/State Route 10 over Johnson Brook in Southwick. Final
    # 57730 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 67099 -- Construction Contract
    – Bridge Replacement (S-22-005) (Concrete) – Route 202 / Route 10 over Johnson Brook. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/08/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/06/1995
    Project Status Advertised 08/28/2010
    Project Management
    100% Design 100% Package Received 05/07/2002
    100% Design 100% Package Comments to DE 09/24/2002
    25% Design 25% Package Received 09/12/2000
    25% Design 25% Package Comments to DE 03/15/2001
    25% Design Design Public Hearing 05/17/2001
    25% Design Design Public Hearing 02/17/2010
    75% Design 75% Package Received 01/29/2002
    75% Design 75% Package Received 04/07/2010
    75% Design 75% Package Comments to DE 03/26/2002
    75% Design 75% Package Comments to DE 05/20/2010
    Final Design PS&E Received 07/09/2010
    Final Design PS&E to FAPRO 08/26/2010
    Consultant Contract Process Scope to DE 02/01/2009
    Consultant Contract Process NTP Issued 06/18/2009
    Consultant Contract Process Workhours Approved 04/28/2009