| Project Description: |
SOUTHWICK- BRIDGE REPLACEMENT, S-22-005, ROUTE 202/ROUTE 10 OVER JOHNSON BROOK
The proposed project consists of the replacement of the bridge which carries U.S. Route 202 and State Route 10 over the Johnson Brook in the same alignment. This replacement will be constructed in three stages. The work will also include improvements to the approach roadway and the relocation of the existing water main.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | James Dalton![]() |
| Estimated Total Contract Cost: | $2,492,838.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 2 |
| Current Status: | This project is in the preliminary design phase. |
|