EASTON- RECONSTRUCTION OF ROUTE 123 (FOUNDRY STREET) FROM NORTON T.L. TO ROUTE 106 (3R PROJECT)
The proposed project consists of roadway improvements along Foundry Street (Route 123), from the Norton/Easton town line to the intersection of Route 106 for a distance a 1.8 miles. The improvements consist of wider travel lanes, paved shoulders to accommodate bicyclists, sidewalks for pedestrians, and a closed drainage system. The proposed work consists of full depth pavement, cold planing and overlay, asphalt berm, sidewalks, wheelchair ramps, pavement markings, and other incidental work.
Location:
  • Town of Easton
  • Resident Engineer: John Bielski
    Construction Contract Value: $4,223,349.14
    Construction Bid Price: $3,405,879.00
    Initial Construction Estimate: $4,261,660.00
    District: District 5

    Contracts (1) Progress
    # 55803 -- Construction Contract
    Easton - Roadway Reconstruction and Related Work on a Section of Route 123 (Foundry Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/18/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 05/10/2008
    Project Management
    100% Design 100% Package Received 08/27/2007
    100% Design 100% Package Comments to DE 12/07/2007
    25% Design 25% Package Received 02/03/2003
    25% Design 25% Package Comments to DE 06/05/2003
    25% Design Design Public Hearing 11/03/2003
    75% Design 75% Package Received 09/07/2004
    75% Design 75% Package Comments to DE 09/20/2006
    Final Design PS&E Received 04/07/2008
    Final Design PS&E to FAPRO 12/21/2007
    Final Design PS&E to FAPRO 05/05/2008