EASTON- RECONSTRUCTION OF ROUTE 123 (FOUNDRY STREET) FROM NORTON T.L. TO ROUTE 106 (3R PROJECT)
The proposed project consists of roadway improvements along Foundry Street (Route 123), from the Norton/Easton town line to the intersection of Route 106 for a distance a 1.8 miles. The improvements consist of wider travel lanes, paved shoulders to accommodate bicyclists, sidewalks for pedestrians, and a closed drainage system. The proposed work consists of full depth pavement, cold planing and overlay, asphalt berm, sidewalks, wheelchair ramps, pavement markings, and other incidental work.
Location:
  • Town of Easton
  • Project Manager: Philip Macdonald
    Estimated Total Contract Cost: $4,223,349.14
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.