| Project Description: |
BROCKTON- RESURFACING AND RELATED WORK ON NORTH MAIN STREET FROM PROSPECT STREET TO AVON T.L. (19,000 FEET)
|
| Location: |
|
| Resident Engineer: | Robert Widden![]() |
| Construction Contract Value: | $1,555,969.68 |
| Construction Bid Price: | $1,776,159.85 |
| Initial Construction Estimate: | $1,792,000.00 |
| District: | District 5 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||