Project Description:
BROCKTON- ROADWAY RECONSTRUCTION ON WEST CHESTNUT ST. FROM PEARL ST. (STA. 1+00 METRIC) TO JUST WEST OF BURKE DRIVE (STA. 14+40)
To improve traffic operations and safety by reconstructing West Chestnut Street from Pearl Street to a point approximately 540 feet east of Knapp Centre in the City of Brockton. The proposed project consists of reconstructing approximately 4,395 feet of West Chestnut Street, including geometric improvement and traffic signal installation at the following three Intersections: West Chestnut Street at Pearl Street; West Chestnut Street at Liberty Street; West Chestnut Street at Manley Street.
Location:
  • City of Brockton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $2,440,299.43
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • B25057 
    See the Milestone Details tab for additional Project information