BROCKTON- ROADWAY RECONSTRUCTION ON WEST CHESTNUT ST. FROM PEARL ST. (STA. 1+00 METRIC) TO JUST WEST OF BURKE DRIVE (STA. 14+40)
To improve traffic operations and safety by reconstructing West Chestnut Street from Pearl Street to a point approximately 540 feet east of Knapp Centre in the City of Brockton. The proposed project consists of reconstructing approximately 4,395 feet of West Chestnut Street, including geometric improvement and traffic signal installation at the following three Intersections: West Chestnut Street at Pearl Street; West Chestnut Street at Liberty Street; West Chestnut Street at Manley Street.
Location:
  • City of Brockton
  • Resident Engineer: Ronald Strangfeld
    Construction Contract Value: $2,440,299.43
    Construction Bid Price: $1,825,415.75
    Initial Construction Estimate: $1,823,772.25
    District: District 5

    Contracts (1) Progress
    # 34448 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of West Chestnut Street. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/08/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/03/2001
    Project Review Committee PRC Approved 08/01/1995
    Project Status Advertised 08/23/2003
    Project Management