Project Description: |
BROCKTON- RECONSTRUCTION OF WINTER STREET, FROM HOWARD STREET TO NORTH CARY STREET (5,300 FEET - 3R PROJECT)
The proposed project includes pavement reconstruction, with some minor widening with granite curbing, installation of new bituminous concrete sidewalks and wheelchair ramps, minor drainage improvements and utility adjustments and/or relocations, pavement markings and a traffic signal with a pedestrian phase at Howard Street intersection.
|
Location: |
|
Resident Engineer: | Ronald Strangfeld |
Construction Contract Value: | $2,864,984.72 |
Construction Bid Price: | $2,132,717.26 |
Initial Construction Estimate: | $2,461,617.00 |
District: | District 5 |
|
Bridges |
|
|
|
|