HAVERHILL- BRIDGE REPLACEMENT, H-12-005, FERRY ROAD OVER THE B&M RAILROAD AND MBTA
This bridge project will result in the removal of the existing bridge and the construction of a new bridge on a new alignment for better sight distance. Work also includes a new storm water drainage system, highway guards, loam and seeding, and other necessary incidental work. A detour will be signed for vehicular traffic during construction of this bridge. 425 feet of the westerly approach roadway and 300 feet of the easterly approach roadway will be reconstructed. Also, 225 feet of South Riverview Street will be reconstructed.
Location:
  • City of Haverhill
  • Resident Engineer: Michael Cannata
    Construction Contract Value: $4,640,543.00
    Construction Bid Price: $3,807,893.08
    Initial Construction Estimate: $4,196,550.00
    District: District 4

    Contracts (5) Progress
    # 30270 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 68207 -- Construction Contract
    Bridge Replacement (H-12-5) (Steel) – Ferry Road over the B & M and MBTA Railroads. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/01/1995
    Project Review Committee Letter 09/25/1995
    Project Status Advertised 06/13/2009
    Project Status Advertised 11/20/2010
    Project Management
    100% Design 100% Package Received 07/11/2008
    100% Design 100% Package Received 02/05/2009
    100% Design 100% Package Comments to DE 02/03/2009
    100% Design 100% Package Comments to DE 03/13/2009
    25% Design 25% Package Received 12/13/2000
    25% Design 25% Package Comments to DE 02/20/2001
    25% Design Design Public Hearing 05/16/2001
    75% Design 75% Package Received 04/04/2003
    75% Design 75% Package Comments to DE 11/18/2004
    Final Design PS&E Received 11/05/2010
    Final Design PS&E to FAPRO 11/17/2010
    Consultant Contract Process NTP Issued 03/22/1996